There took place a ceremony of construction works completion and start-up of commissioning works. Representatives of state governmental authorities, the plant staff, the manageing company, business and bank structures participated in this event.
25/07/2006
Ceremony of the plant start-up is due on July 29, 2006, Saturday, at 10-00. Concerning accreditation of mass-media put through to number 7 (3452) 28-43-01 in Tyumen and 7 (495) 782-15-30 in Moscow.
17/06/2006
Ceremony of the plant start-up timed to Tyumen-s 420th anniversary, the city holiday, is due on July 29, Saturday.
15/06/2006
The plant start-up is due in July 2006.
14/06/2006
Volume of Antipinsky OPP connection to TU with the amount of 1700 thousand tons per year is agreed upon with AK Transneft.
22/05/2006
Due to the expected start-up of the plant numerous vacancies are available now.
28/04/2006
The first steam generators mounted. Process pipeline fitting started.
24/04/2006
Revision of the KIPiA and adobe equipment.
21/04/2006
Completion of railway sidings and overhead roads metal constructions for running into railway tanks.
17/04/2006
Flare separator and flare boom mounted.
05/04/2006
Tank battery construction nearly completed.
22/03/2006
Unique boiler machinery, having no Russian analogues, delivered from India.
08/03/2006
SC TYumepromstroi jointly with the Russian Railways (RZhD) started railways construction.
20/02/2006
Plant shareholders Revision Committee visits and monitors the construction plant.
19/10/2005
General contractor started development of the tank battery.
18/09/2005
Pad work for the tank battery completed. Over 28 thousand tons of sand applied.
10/09/2005
Finishing of the administrative building completed. The plant administration moved to the new building.
19/08/2005
Last week laying of the main motor roads in the plant territory completed, which ensures free passage of machines under spring and autumn weather conditions.
15/08/2005
Governor of Tyumen Region Sergey Sobyanin visited the plant.
21/07/2005
Basic technological equipment mounted.
18/06/2005
Agreement with Petrofac Company on supply of additional equipment concluded.
12/06/2005

First line atmospheric tower installed.
24/05/2005
Production buildings and mounting works on water supply and sewage systems completed.
19/05/2005
General contractor started mounting of technological equipment.
06/05/2005
Preparation for battery park hydrotesting in process.
09/02/2005
General contractor, SC Tyumenpromstroi started works on the plant site.
23/01/2005
General design engineer OAO Neftekhimproekt completed design and estimate documentation. Correction of the project technological sector nearly completed.
12/12/2004
Equipment supplier confirmed readiness for mounting works, supervising installation and designer supervision.
30/11/2004
The land plot prepared for construction works.
10/11/2004
Basic technological equipment supplied and stored at temporary storage warehouses.
09/06/2004
General Meeting of ZAO Antipinsky OPP shareholders decided on resuming of an oil processing plant construction in Tyumen Region (Tyumen, village of Antipino).
|