October 19, 2005
The General Contractor got down to the construction of the tank battery.
|
|
September 18, 2005
Pad work for the tank battery has been completed. More than 28 thousand cum of sand have been supplied.
|
|
September 10, 2005
The finishing of the administration and on-site facilities has been completed. The administrative personnel of the refinery has moved to a new building.
|
|
August 19, 2005
Last week the laying of main motor roads on the territory of the enterprise was completed what will ensure a stable transit of technology in the autumn and spring seasons.
|
|
August 15, 2005
Governor Sergei Sobyanin of the Tyumen Region visited the refinery.
|
|
July 21, 2005
The core process equipment is completely installed.
|
|
June 18, 2005
Additional equipment delivery agreement has been reached with Petrofac company.
|
|
June 12, 2005
The crude distillation unit of the first phase has been installed.
|
|
May 24, 2005
The production facilities have been built, the construction and assembly works at the water supply and sewage systems networks have been completed.
|
|
May 19, 2005
The General Contractor started the installation of technological equipment.
|
|
February 9, 2005
The General Contractor, Tyumenpromstroi Building Company started the works on the refinery’s site.
|
|
January 23, 2005
General Designer Neftekhimproekt OJSC completed the drawing up of design and estimate documentation needed for the construction. The process of amending the engineering aspect of the design is nearing completion.
|
|